Skip to Content

Yuma Road Report, Week of Aug. 1

Here is a list of the upcoming road projects scheduled for the streets of Yuma:

City Projects

1st Avenue reconstruction project

The City is reconstructing 1st Avenue between 16th Street and Orange Avenue, including improvements to underground water/sewer infrastructure, to sidewalks and driveways, and to surface pavement. Right now, 1st Avenue is fully closed from 11th Street to 16th Street. As soon as Friday, Aug. 2, the 1st Avenue will be extended to the south side of the intersection with 10th Street and be in effect for three weeks.

Work on 16th Street has been substantially completed and all lanes of traffic are now open on 16th .

Southwest Gas is currently working in 1st Avenue north of the City’s project. Through Friday, Aug. 2, 1st Avenue will be closed between 8th Street and 9th Street for installation of gas service. Work hours will be between 5:30 a.m. and 4 p.m. Gas line work may continue to move north on 1st Avenue as sections become complete.

City Street Maintenance

Street maintenance operations for Aug. 5-9 will take place in the following locations.

Crack seal operations

Falls Ranch #1 and # 3

16th Street from 14th Avenue to Avenue B

24th Street from Araby Road to Avenue 9E

Thermal patching

Avenue 3E, southbound lane near MCAS — work limited from 6:30 to 8:30 a.m.

Pedestrian crosswalk repairs

While students are off for summer break, Public Works will perform crosswalk maintenance around school zones. The goal is to ensure all designated crosswalks are well-marked for the upcoming school year. The following schools will be reviewed and repaired: Yuma High, O.C. Johnson, Alice Byrne, Amerischools , St. Francis and Mesquite.

Other utility projects and encroachment permits

8th Street, Avenue C to Avenue D (Yuma County)

Yuma County is reconstructing and widening 8th Street between Avenue C and Avenue D. The work includes widening the roadway to a 5-lane section with sidewalks, streetlights and drainage improvements. Currently, there is shoulder work taking place on the north side of the roadway through December. In the future, the roadway will be closed to through-traffic, but access will be maintained to local homes and businesses. Completion of the collaborative project is anticipated by early November.

Avenue B, 16th Street to 20th Street (SW Gas)

A contractor working for Southwest Gas will replace a gas line on Avenue B from 16th Street to 20th Street, with work in cross streets 24th Street, 25th Street, 26th Street and 32nd Street. Project will run the end of September. Expect lane closures on Avenue B and some possible turn restrictions.

25th-27th streets, Virginia Drive (SW Gas)

From Aug. 1 through as long as Dec. 1, Southwest Gas contractors will be replacing main lines in the areas between 4th Avenue and 1st Avenue and between 25th Street and 27th Street. Affected streets will include 25th Street, Virginia Drive, 27th Street, and the alley between Maple and Hacienda.

24th Street, Avenue 9E (SW Gas)

Gas line pipe replacement will bring lane restrictions to 24th Street approaching Avenue 9E from the west. Work is expected to wrap by Sept. 13.

24th Street, 46th Drive to Avenue D ( APS )

APS work will require a hard closure of 24th Street between 46th Drive and Avenue D through Sept. 6. Detours will be 20th Street or 32nd Street.

Avenue 7E south of 24th Street (SW Gas)

Southwest Gas will be working on service stub lines along Avenue 7E and intersecting side streets south of 24th Street through October. Lanes will be narrowed in work zones.

Avenue C at 16th Street

The right southbound lane of Avenue C will be closed approaching 16th Street for upcoming pavement replacement at H.L. Suverkrup Elementary School parking lot. Exact project dates were not available; however, permit stipulates work will be completed by Oct. 25.

12th Street west of Avenue A (SW Gas)

12th Street will be closed immediately west of Avenue A for gas line replacement. Detour is 11th Street. Exact work dates were unavailable; however, the permit expires Oct. 25.

16th Street, Yuma Palms ( TrueNet )

Aug. 12-19, the right westbound turn lane of 16th Street turning onto northbound Yuma Palms Parkway will be closed for telecommunications fiber installation.

32nd Street, Avenue 8-1/2E

Private installation of driveway turnouts will require right-lane restrictions on eastbound 32nd Street approaching and continuing on southbound Avenue 8-1/2E through Aug. 31.

32nd Street shoulder work (Century Link)

Century Link will be working on its infrastructure in manholes on the shoulder of 32nd Street between Avenue 3E and Avenue 8E. While no lane closures are expected, motorists are asked to be aware of workers and drive with caution. Work will conclude by mid-September.

Avenue 6E, near 44th Place ( APS )

APS is working in the shoulder of Avenue 6E near 44th Place to install infrastructure for the Driftwood subdivisions. No lane closures are in effect; however, motorists are advised to drive with caution near workers.

Avenue 3E, near MCAS Main Gate ( APS )

APS will work in the northbound shoulder of Avenue 3E near the MCAS Main Gate for switch replacement on a pole. Time frame for this single-day project is Aug. 5-9.

Avenue C, near 28th Street (Water Users)

Avenue C will be narrowed with reduced speed limit in a zone 500-feet on both sides of the intersection with 28th Street for irrigation canal culvert work by Yuma County Water Users’ Association. This is a 5-day project; however, start date has not yet been finalized.

3rd Street, 13th-25th avenues (Century Link)

Telephone cable maintenance will cause lane narrowing on 3rd Street between 13th Avenue and 25th Avenue. Work will conclude no later than mid-August.

3rd Street, 4th-5th avenues ( APS )

The right eastbound lane of 3rd Avenue will be narrowed between 5th Avenue and 4th Avenue for APS pole work. This is a 5-day project.

24th Street at Avenue 9E (SW Gas)

Southwest Gas is conducting main pipe replace on 24th Street west of Avenue 9E. Lane restrictions, speed limit reduction and bike lane closure will take place. This section is part of a larger project on 24th Street expected to wrap by September.

3rd Street, 4th Avenue – Avenue A (Century Link)

Century Link has a five-month project to repair telephone cable along 3rd Street, between 4th Avenue and Avenue A. The project which will involve accessing manholes will cause lane closures and in some areas sidewalk closures.

Avenue 3E at 40th Street, 32nd Street

There will be lane closures along Avenue 3E at 40th Street, 32nd Street and at the intersection of Avenue 4E and 41st place through Aug. 6 for a Century Link project that requires access to manholes. A reduced speed limit will also be in place.

APS pole work, various locations ( APS )

APS will conduct pole maintenance and install new infrastructure on existing poles throughout the area through September 2019. While work will mostly occur on shoulders, some lane narrowing and shifting will take place within work zones. Work zones the City is aware of include the following:

Avenue A west of 21st Street.
Avenue 3E north of 40th Street.
32nd Street from Avenue C and 28th Drive.
Avenue 4E and 36th Street.
3rd Street east of Avenue B.
Avenue A at the northeast corner of 16th Street.
15th Street and Avenue A.
32nd Street at S.R. 195.
37th Street at Avenue 5E.
North Frontage Road and Mesa Avenue.
Avenue 8E south of 24th Street.
12th Avenue south of 7th Street.
Araby Road south of 24th Street.
County 11th Street and Westwind .
Near the corner of Avenue 5E and E. County 10th Street.
South Frontage Road near Avenue 9E.

Article Topic Follows: News

Jump to comments ↓

KYMA News Team

BE PART OF THE CONVERSATION

KYMA KECY is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content